Wilma Kenny | Jul 10, 2014
Financial Audit Report
Howard Allan, a Chartered Accountant from Perth, reviewed his company’s audit of South Frontenac’s 2013 finances. Mr Allan made it clear that his approach was broader than merely reviewing the financial statements; it included a thorough review of governance policies and administrative and decision-making processes relating to “The orderly and efficient conduct of the Township’s business.”
Although he made a few minor recommendations, Allan’s overall report was very positive. He complimented staff on their cooperation, high level of professionalism and well-maintained records. “The Township’s financial position is strong.”
Development Charges Update
South Frontenac is the only Township in the County that presently levies development charges. A development charge is a fee that may be added to residential building permits, to help offset the increased costs of providing services to the new residents. Although the highest percentage of the charge goes to public works (roads, bridges, equipment), money is also apportioned to fire protection, police services, general government, recreation and libraries. A public meeting to review the Ainsley Group’s background study and recommendations on the Township’s charges drew no comments from the floor. An updated fee schedule will be incorporated into a by-law this fall.
Proposed Signage By-law
Public Works Manager Mark Segsworth brought a draft by-law intended to address the proliferation of signs within some of the Township’s road allowances. He said that the question of commercial signage (which includes the blue ‘government-looking’ tourism signs) will need further discussion: should the Township rent road allowance space, or restrict commercial signs to a specific distance from the road?
Long Swamp Bridge to Remain Closed for Now
The roads department has just received a draft version of the Long Swamp bridge assessment, and has not had time to thoroughly review it. The options listed are: 1) do nothing/confirm load posting, 2) remove bridge and close road, 3) strengthen existing bridge, and 4) replace with new structure. Projected costs of these options run from $5,000 to $200,000.
Council accepted Segsworth’s recommendation that the Long Swamp Road remain temporarily closed until this issue has been resolved.
More Stories
- Kaladar Station - Sometimes the timing is just right
- 50th Anniversary Party for Rural Frontenac Community Services
- Bioblitz Coming This Week at Piccadilly Property
- Committee recommends looking at an accommodation tax in Frontenac County
- Bobs and Crow Lake Shoreline Restoration
- Ellen Fraser is recognized as the winner of the 2025 MERA Award of Excellence in Fine Art and Fine Craft.
- Addington Highlands Treads Lightly Into F Carney Flag Debate Territory
- Simonett Purchase Raises Questions
- Why This Green Could Not Vote Red
- The Sand Is Still Coloured